Friday, August 28, 2009
Coupeville Library Expansion -- Week 7
Week 7 proved to be a banner week in terms of visual changes at the Library expansion project. Pre-constructed wall panels arrived on Monday and by Tuesday evening the form of the new Library began to emerge. The photos below provide some detail of the changes as they occurred.
Wall panels arrived and were stacked on the concrete floor in the new addition.
Saturday, August 22, 2009
Coupeville Library Expansion -- Week 6
This was a good week on the Library Expansion project. Forming for the concrete floor, insertion of the rebar, and completion of all plumbing, electrical and data piping under the concrete floor was completed by Thursday. At 7 AM on Friday, work began pouring the concrete floor and it was completed by noon. Below are some photos of the weeks work.
The forms and rebar are in place and awaiting concrete for the new floor.
Another view of the preparations for the concrete floor in the expanded section of the library.
This is Darren Leyenhorst, construction superintendent. He seems forever to be on the phone to keep things moving forward. We are about a week ahead of schedule currently.
The cement pump arrives at 7AM Friday -- ready to start pouring the new floor
In this photo, about 1/2 of the floor has been poured and the work continues.
The workman use a long vibrating device to assure the floor is level and that no voids occur under the surface. One workman is holding the hose that is delivering cement to be leveled.
Troweling begins. The workman on the right is doing the finish work along the edge of the floor.
Monday, August 17, 2009
Coupeville Library Expansion -- Week 5
to the right are conduits for electrical and computer connections in the concrete floor. The
vertical white pipe is a sewer line vent that will extend through the roof of the new building.
six inch thickness of the old library concrete floors.
fully air conditioned!!
Coupeville Library Expansion -- Week 4
Coupeville Library Expansion -- Week 3
Coupeville Library Expansion -- Week 2
Coupeville Library Expansion--Before the Project Began
Subscribe to:
Posts (Atom)