Week 27 saw more progress at the Library as the carpet installers arrived and began laying the carpet. The carpet consists of 2 foot by 2 foot squares that fit together nicely and can be easily replaced if damage occurs to any one of the squares. There was also more progress in hanging interior doors and installing trim around the doors. Outside, the inclement weather provided a break on Thursday and the final section of the handicap access sidewalk to the front door was poured. It was immediately covered to protect it from rain in case there was not enough time for it to become cured and hard.
The carpeting was completed in the stacks area on Friday and a workman is rolling it to be sure it is fully set in the glue that will hold it in place. A dark brown rubber baseboard will be glued in place along the wall when all the carpet has been laid and in place.
These doors were installed this week and will secure the entrance to the storage room in the Community Meeting room.
Outside the sidewalk for handicap access to the front door of the library was completed but covered before more rain arrived in the area. Parking areas at the rear of the building remain to be finished.
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment