Week 25 was a short week between Christmas and the start of the New Year but progress was made as usual. The photos below show a few more additions to the project as we move ever closer to finishing the expansion project.

The ceiling in the hallway between the front and rear doors of the Library is now complete with the installation 4 inch finished wood slats. They provide a nice ceiling contrast to the much lighter panels that make up the ceilings in the rest of the Library.

The first of the wooden desks and cabinets have appeared in the circulation desk areas. Not to worry -- the faces peering out of the inside book drop will not be a permanent part of the Library scene. They were Christmas visitors for California who thought they could enhance this photo!

This is a view into the children's room and shows a low cabinet that will provide display space for children entering the room.


Outside, progress was made on the sidewalk the will provide nearly level access to the front door of the Library. This concrete will be poured next week.


Additional outside work was done to prepare for pouring the sidewalk extending from the front of the Library toward downtown Coupeville and the wharf. The concrete will also be poured next week and will provide ready access to and from Front Street in Coupeville.