Week 14 saw more changes at the library. The front entrance is being completed. Insulation of the exterior walls and some interior walls has begun in preparation for interior sheet rock walls. Exterior siding has begun and most of the exterior siding should be completed next week. Fortunately window installation is nearly complete and the roof has been shingled -- just ahead of two nights of rain during the week. The photos below show some of the progress and changes this week.
The front steps to the library are taking shape. A handicap sidewalk entrance will be poured to the left of the steps above the rock wall.
Insulation is being installed in exterior walls as well as some interior walls for sound proofing.
The air-conditioning and heating units have arrived. Interior
ductwork is already completed. Note also our first look at the siding for the building. Of course, it will be a different color when the exterior painting is completed.
Another view of the exterior siding -- applied to one side of the
cupolo so far.
A later view of more side applied on the west side of the building. Most of the siding should be installed by the end of next week.