Week 16 saw continued progress. Siding on the west side of the building has now been completed although much remains to be done on the rest of the building. A rough estimate would be that about 50% of the siding has now been installed. Interior work continued during the week. Installation of sheet rock was completed and work began taping the seams. The remaining two (of four) solar tubes bringing light in from the cupola were also installed. The photos below show some of the progress made during the week.
Siding on the west side of the building is now complete but siding work remains to be done.
An interior view of the room where the stacks will be located. Note that the seams have now been taped although the final finishing of the seams remains to be done. The final result will be
seams that are completely invisible.