Another week of progress at the Library. The right front window in the adult reading room has finally been installed after delays in getting some of the need framing. All the windows are now in place. Sheet rock installation and finishing was also completed during the week and interior painting was to begin on Friday. Additional outside siding was installed on the east side of the building. Next week we should see installation of the fireplace and the airconditioning units. Following are some photos showing progress.
The right side front window has been installed. Window installation is now complete.